Which one of the following statements is not correct with regard to heading and henching method of tunnelling?

  • ADriving of tunnel is done in two portions of its section
  • BDriving the top portion is done in advance of the bottom portion
  • CThe holes in head and bench are loaded together with explosive for blasting
  • DFiring of head holes is done just before the bench holes are fired
Correct Answer : (D)

Firing of head holes is done just before the bench holes are fired