Q.

Load flow studies must be made on a power system before

  • AMaking short-circuit studies but not for transient stability studies on the power system.
  • BMaking transient stability studies but not for short-circuits studies on the power system.
  • CMaking both short-circuit and transient stability studies on the power system.
  • DFor neither Making short-circuit studies nor transient stability studies on the power system.
Correct Answer : (C)

Making both short-circuit and transient stability studies on the power system.

Hints :
Previous

The most serious consequence of a major uncleared short-circuit fault could be

Next

Which of the following results in a symmetrical fault?