Q.

The main purpose of performing open circuit on a transformer is to measure its 

  • ACopper loss
  • BCore loss
  • CTotal loss
  • DInsulation resistance
Correct Answer : (B)

Core loss

Hints :

The main purpose of performing open circuit on a transformer is to measure its Core loss.