Q.

Activity slack or float of any event on a PERT/CPM chart is represented by

  • ALatest start time of succeeding event earliest finish time of preceding event activity time
  • BLatest start time of the event earliest start time of the event
  • CLatest finish time of event earliest finish time of the event
  • DAnyone of the above
Correct Answer : (D)

Anyone of the above

Hints :