Q.

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

  • ALatest start time earliest start time
  • BLatest finish time earliest finish time (EFT)
  • CTLEFT
  • DAll of the above
Correct Answer : (D)

All of the above

Hints :