Q.

Pessimistic time is

  • AThe maximum time which an activity might require
  • BThe average time required for a job
  • CThe most probable time considering all conditions
  • DThe minimum time in which an activity can possibly be accomplished
Correct Answer : (A)

The maximum time which an activity might require

Hints :