Q.

Standard time is equal to

  • A(Normal time) - (allowances)
  • B(Normal time) + (allowances)
  • CRepresentative time multiplied by rating factor
  • DNormal time taken by an operation
Correct Answer : (B)

(Normal time) + (allowances)

Hints :