Q.

The essential condition for the decompression of an activity is that

  • AThe project time should change due to decompression
  • BAfter decompression the time of an activity invariably exceeds its normal time
  • CAn activity could be decompressed to the maximum extent of its normal time
  • DNone of the above
Correct Answer : (C)

An activity could be decompressed to the maximum extent of its normal time

Hints :
Previous

A dummy activity

Next

The term 'value' in value engineering refers to

Join The Discussion