Pick up the incorrect statement from the following. A critical ratio scheduling

  • AEstablishes the relative priorities among various activities on a common basis
  • BDetermines the status of each activity
  • CAdjusts automatically changes in activity progress
  • DNone of the above
Correct Answer : (D)

None of the above

Hints :
Previous

The work study is done by means of

Next

In break-even analysis, total cost consists of